Introduction to this Part

This Part sets out the requirements for a roof drainage system.

Objectives

NCC Blurbs

The objective of this part is to—

  1. safeguard people from illness, injury or loss (including loss of amenity) due to the failure of a roof drainage installation; and
  2. ensure that a roof drainage installation is adequate; and
  3. conserve water and energy; and
  4. safeguard the environment; and
  5. safeguard public and private infrastructure; and
  6. ensure that a roof drainage installation is designed and is capable of being maintained so that throughout its serviceable life it will continue to satisfy Objectives (a) to (e).
NCC Title

Objective

NCC State
TAS
NCC SPTC Current
Objective

Functional Statements

NCC Blurbs

Buildings are to be provided with roof drainage to provide protection to people, property and the environment from adverse effects of stormwater.

NCC Title

Functional statements

NCC State
TAS
NCC SPTC Current
Functional statements

Performance Requirements

NCC Blurbs

(1) A roof drainage system must have the capacity to transfer the volume of water anticipated in a 5% annual exceedance probability rainfall event.

(2) Box and valley gutters must have capacity to transfer the volume of water anticipated in a 1% annual exceedance probability rainfall event.

(3) The annual exceedance probability must be appropriate to—

  1. the importance of the building; and
  2. the severity of potential damage to the property; and
  3. The severity of loss of amenity, illness or injury that would result from the failure of the system.
NCC Title

Roof drainage systems

NCC State
TAS
NCC SPTC Current
Roof drainage systems
NCC Blurbs

A roof drainage system must provide an overflow device suitable for a 1% annual exceedance probability rainfall event.

NCC Title

Overflow

NCC State
TAS
NCC SPTC Current
Overflow
NCC Blurbs

All internal roof drainage components must be watertight.

NCC Title

Watertightness

NCC State
TAS
NCC SPTC Current
Watertightness
NCC Blurbs

(1) A roof drainage system must ensure that—

  1. stormwater is transferred to a Network Utility Operator's stormwater system or an approved disposal system; and
  2. appropriate access is provided for maintenance and clearing blockages.

(2) A roof drainage installation must avoid blockage and uncontrolled discharge causing—

  1. loss of amenity; and
  2. loss to building and property.

(3) A roof drainage installation must avoid foul air and gasses accumulating in the roof drainage system.

NCC Title

Design, construction and installation

NCC State
TAS
NCC SPTC Current
Design, construction and installation

Deemed-to-Satisfy Provisions

NCC Blurbs

Performance Requirements E3P1 to E3P4 are satisfied by complying with E3D2 and E3D3.

NCC Title

Application

NCC State
TAS
NCC SPTC Current
Application
NCC Blurbs

A roof drainage system must comply with—

  1. AS/NZS 3500.3; or
  2. Housing Provisions 7.4
NCC Title

General requirements

NCC State
TAS
NCC SPTC Current
General requirements
NCC Blurbs

(1) When a liquid trade waste generating process does not fully occur within a building, suitable roofing must prevent the entry of stormwater to the disposal system.

(2) When a liquid trade waste generating process occurs within a building where one or more sides are open to the weather, a vertical overhang of a minimum of 10° from the roofing must be provided.

(3) Where the wind driven rainwater is likely to enter under the roof in extreme storm conditions, the roof must overhang by a minimum of 10° from the roofing.

Explanatory information

TAS Figure E3D3 provides an example of a suitable installation practice to meet the requirements of E3D3(3).

Insert TAS figure (E3D3 explanatory) as follows:
TAS Figure E3D3 explanatory: Roofing of liquid trade waste areas
image-E3D3-roofing-of-liquid-trade-waste-areas-TAS.svg
NCC Title

Roofing of liquid trade waste generation areas

NCC State
TAS
NCC SPTC Current
Roofing of liquid trade waste generation areas