TAS Part E2 Heating, cooling and ventilation systems

TAS Part E2 Heating, cooling and ventilation systems

Introduction to this Part

This Part sets out the requirements for mechanical heating, cooling and ventilation systems.

Objectives

NCC Blurbs

The Objective of this Part is to—

  1. safeguard people from illness, injury or loss (including loss of amenity) due to the failure of a heating, ventilation or air-conditioning installation; and
  2. ensure that a heating, ventilation or air-conditioning installation is suitable; and
  3. conserve water and energy; and
  4. safeguard the environment; and
  5. safeguard public and private infrastructure; and
  6. ensure that a heating, ventilation or air-conditioning installation is designed and is capable of being maintained so that throughout its serviceable life it will continue to satisfy Objectives (a) to (e).
NCC Title

Objective

NCC State
TAS
NCC SPTC Current
Objective

Functional Statements

NCC Blurbs

Mechanical services, plant and equipment used for heating, cooling and/or ventilation of a building must be adequate for their intended purpose.

NCC Title

Functional statement 1

NCC State
TAS
NCC SPTC Current
Functional statement 1
NCC Blurbs

A heating, cooling and/or ventilation system must support energy efficient outcomes and minimise any impact on building occupants of adjoining spaces, the Network Utility Operator's infrastructure, property and environment.

NCC Title

Functional statement 2

NCC State
TAS
NCC SPTC Current
Functional statement 2

Performance Requirements

NCC Blurbs

(1) A mechanical service, plant and equipment for heating, cooling and/or ventilation must avoid the following:

  1. Damage to property.
  2. Loss of amenity to occupants.

(2) A mechanical service, plant and equipment for heating, cooling and/or ventilation must ensure the following:

  1. Efficient use of energy and water.
  2. Access for maintenance.
NCC Title

Design, construction, installation and maintenance

NCC State
TAS
NCC SPTC Current
Design, construction, installation and maintenance
NCC Blurbs

Pressure equipment used in mechanical heating, cooling and ventilation systems must avoid the likelihood of explosion, rupture or leakage.

NCC Title

Pressure equipment

NCC State
TAS
NCC SPTC Current
Pressure equipment
NCC Blurbs

Mechanical air-handling and cooling water systems installed in a building must control the accumulation of microbial growth.

NCC Title

Microbial control

NCC State
TAS
NCC SPTC Current
Microbial control

Deemed-to-Satisfy Provisions

NCC Blurbs

Performance Requirement E2P1 to E2P3 are satisfied by complying with E2D2.

NCC Title

Application

NCC State
TAS
NCC SPTC Current
Application
NCC Blurbs

(1) Mechanical ventilation and air-conditioning systems for must comply with the requirements of the relevant Parts of:

  1. NCC Volume One for Class 2 to 9 Buildings; or
  2. NCC Volume Two for Class 1 and 10 Buildings.

(2) Mechanical ventilation and air-conditioning equipment must be in accordance with:

  1. AS/NZS 1200,
  2. AS 1324.1 for the application, performance and construction for air filters for use in general ventilation and air-conditioning,
  3. AS 1345 for the identification of the contents of pipes, conduits and ducts,
  4. AS/NZS 1668.1 for the use of mechanical ventilation and air-conditioning in buildings for fire and smoke control in multi-compartment buildings,
  5. AS 1668.2 for the use of mechanical ventilation and air-conditioning in buildings for mechanical ventilation,
  6. AS/NZS 3500.1 for the design, installation, alteration, addition, repair and commissioning of cold water services,
  7. AS/NZS 3500.2 for the design, installation, alteration, addition and repair of sanitary plumbing and drainage,
  8. AS/NZS 3500.4 for the design, installation, commissioning, alteration, addition and repair of heated water services,
  9. AS 4254.1 for flexible ductwork for air-handling systems in buildings,
  10. AS 4254.2 for the rigid ductwork for air-handling systems in buildings,
  11. AS 4426 for the selection, installation and finish of thermal insulation of pipework, ductwork and equipment.
  12. AS 4508 for the thermal resistance of insulation for ductwork used in building air-conditioning, and
  13. AS 5601 for gas installations.

(3) Copper piping for air-conditioning and refrigeration must be in accordance with AS/NZS 1571.

NCC Title

General requirements

NCC State
TAS
NCC SPTC Current
General requirements